Do I Need a Building Permit?
Building permits are required for the construction of new buildings and structures including additions and alterations to existing buildings.
Before you start construction
Did you recently receive a Development Approval (DA) for a structure or building? You will now be required to submit a Building Permit Application before you commence construction of any buildings or structures listed below.
When the building permit has been issued to you, only then are you free to construct as per the approved plans and technical documents.
On this page
Work requiring a building permit
General building work that will require a building permit includes:
- Swimming pools and spas
- Swimming pool security/safety barriers
- Fences (not masonry) over 1.8m in height
- Fences (masonry) over 750mm in height
- Sheds, garages, lean-to and workshops (some exemptions apply)
- Patios, verandahs, gazebos, shade sails and pergolas (some exemptions apply)
- Retaining walls in excess of 500mm in height
- Residential dwellings
- "Tiny" homes
- Earthworks and sand pads
- Sea Containers (for permanent storage use and will be on the property for greater than one calendar month)
- Additions and alterations to residential dwellings, including granny flats and ancillary dwellings
- Commercial buildings, including fit-outs and refurbishments
- Industrial buildings
- Water tanks with a capacity greater than 5000 litres
Work valued at more than $20,000
In most cases where the total value of the work exceeds $20,000, a permit can only be issued to a registered builder or in some circumstances an owner builder. More information is available at the Building Commission website.
Department of Mines, Industry Regulation and Safety – Building Commission
Certificates of Design Compliance
If submitting a Certified Building Application, you are required to obtain a Certificate of Design Compliance from a Registered Building Surveyor. A list of registered building surveyors in Western Australia can be found here.
If submitting an Uncertified Building Application or BA2, the Shire will issue this Certificate of Design Compliance with the building permit. At this point in time, the Shire of Serpentine Jarrahdale will only issue these Certificates of Design Compliance for buildings classed 1a, 10a, 10b and 10c.
Will any other approvals be required?
Fun Fact: Did you know 80-90% of Building Permits are applied for and held up and sometimes refused without proper consideration for the Shire’s planning and health requirements?
It is important to speak to our planning and health teams about your project before finalising and submitting your building application. This will ensure a smoother and more efficient building approval experience.
Residential Applications
Building permit applications may be lodged with the Shire of Serpentine Jarrahdale as either a certified application or an uncertified application.
Certified applications will require a Certificate of Design Compliance from a registered independent Building Surveyor contractor. The Shire’s Building Surveyors will be responsible for issuing Certificates of Design Compliance for uncertified applications.
The Shire is the authority for issuing Building Permits for proposed building works within its jurisdiction.
Residential application forms
Commercial and Industrial Applications
All commercial and industrial applications will need to lodge a certified application and will require a Certificate of Design Compliance from a West Australian Registered Independent Building Surveyor contractor.
Commercial and industrial application forms
Processing Applications
Uncertified Applications
It can take up to 25 business days from the date of lodgement to determine an uncertified application and issue a permit.
During the assessment period, if the Shire determines that further information is required the applicant will be contacted and requested to provide the outstanding information.
Where it is determined that a Development Approval is required an applicant may request that their building application is placed on hold pending the outcome of the Development Application. Building Permits cannot be issued if Development Approval is required.
Certified Applications
It can take up to 10 business days from the date of lodgement to determine a certified application.
During the assessment period, if the Shire determines that further information is required the applicant will be contacted and requested to provide the outstanding information.
Where it is determined that a Development Approval is required an applicant may request that their building application is placed on hold pending the outcome of the Development Application. Building Permits cannot be issued if Development approval is required.
Notices of Completion and Occupancy Permits
Upon the completion of all works for which a building permit has been issued the nominated builder(s) are required to provide the Shire a Notice of Completion within 7 days of construction finishing.
All builders responsible for the construction of commercial works are required to provide the Shire with a Notice of Completion and a Certificate of Construction Compliance before any commercial or industrial building can be occupied.
Single dwellings and incidental structures (Classes 1a, 10a, 10b and 10c) do not require occupancy permits.
Completion and refund forms
Request for Building Plans
To request building plans for your property held by the Shire, please complete the below form and email to info@sjshire.wa.gov.au for processing.
If you would like to know what plans are available before completing the form, please contact the Shire on 9526 1111.
Request for Building Plans via SJ Shire Online
Stormwater and Easement Requirements
Stormwater is surface water that originates during rains.
Property owners have a statutory obligation under common law precedents and a section in the Local Government Act 1995 to confine stormwater within their boundaries.
This can be achieved by collecting stormwater in rainwater tanks, by delivering it to soakwells within your property or where available by making a connection to piped stormwater infrastructure.
For more information, visit our Stormwater and Drainage page.