Menu

Abernethy Road, Byford

Roadworks, updates and general information regarding the Abernethy Road Project upgrade.

Downloads

Complete Plan

Abernethy road map Base Plan NEW3

Latest update

Road Closures

Update as of 5pm, August 28

 

Temporary Westbound lane closure of Abernethy Road, between Warrington Road to Gordin Way September 2 - September 30

 

The Shire advises road users of the upcoming closure on Abernethy Road;

 

1. Abernethy Road, between Gordin Way and Warrington Road– eastbound lane will remain open (heading towards South Western Highway). Westbound lane will be closed (heading towards Hopkinson Road) and traffic detoured from Gordin Way through Mead Street to Warrington Road

 

2. Abernethy Road, between Warrington Road to Hopkinson Road will remain open in both lanes

 

3. Abernethy road, between South Western Highway and Gordin Way will remain open in both lanes.

 

The proposed closure is for the purpose of the Abernethy Road Upgrade. The closure will commence on Monday 2 September 2019 and is expected to be completed on Monday 30 September 2019. 

 

Residents are asked to please be aware of the traffic control affecting your street. If traffic control is not present as you exit your street, please exit with the traffic flow with care.

 

Please note that the businesses on Abernethy Road & George Street will remain open during normal opening hours.

 

Please see detour map below.

 

If you require any further information, please contact the Shire on 9526 1111 or info@sjshire.wa.gov.au

 

2019 Abernethy Road Map From September 2 web

Download Detour Map.

 

 

Transperth Bus Detours: 

 

To view bus detours and for more information go to www.transperth.wa.gov.au and view the Journey Planner.

 


Frequently Asked Questions

Here is some frequently asked questions from residents, regarding the Abernethy Road Project:

Will there be trees removed on Abernethy Road?

Yes, trees will be removed to allow space for the widening of Abernethy Road however the Shire is working with the contractor to keep it to a minimum. Once the works are completed, the Shire will develop a planting program to replace trees removed as part of this project.

Why are trees and shrubs being removed on Abernethy Road?

During the design of Abernethy Road, Shire officers considered all options and it was identified that certain trees and shrubs had to be removed for the purpose of the widening of the road, future drainage maintenance, costs of road maintenance and ensuring longevity of the road’s overall life.

When will the trees and shrubs be removed?

As upgrade works progress along Abernethy Road, identified trees and shrubs will be removed in a staged approach, dependent of the works program.

Has the Shire got permission to remove the trees and shrubs?

A clearing permit has been issued by the Department of Environment Regulation to remove the trees and shrubs.

How many trees will be removed?

The engineering drawings for the Abernethy Road project identifies the removal of approximately 120 trees and shrubs, ranging in size. The Shire is working with the contractor, Wormall Civil, to reduce this number where possible.

Will the trees be replaced?

Yes. In line with the aspirations of the Shire’s recently adopted Urban and Rural Forest Strategy, the Shire is committed to retaining the current level of canopy cover within the Shire.

In 2019/20 the Shire has committed funds for 6150 tree seedlings to be planted. This will be delivered through the Shire’s free verge plant program, SJ Landcare and tree planting by our operations team.

For the current financial year, the Shire has funded nearly 6000 new tree seedlings which have been planted. This includes 2240 through the Shire’s free verge plant program, 3376 via SJ Landcare and 129 planted by our operations team.

What is happening on Renaud Way?

The Shire’s contractors are removing vegetation, to install a drainage basin. The purpose of the drainage basin is to store the surface water from Abernethy Road when a rain event occurs. The basin will also help control the outflow into the existing creek.

Will there be dust on site?

With any roadworks, there is potential for dust. The Shire’s contractors have dust management processes in place for when this occurs.

Will there be updates on the project?

The Shire will be providing fortnightly updates on the project on this page and Facebook page. Please visit these sites for the latest information about this project.

When will Abernethy Road be completed?

Abernethy Road is expected to be completed in the last quarter of 2019.

Will the delays driving through Byford affect me, particularly around the schools?

Due to the works, you may be affected by detours. The Shire will provide notice of any detours in place. Please allow extra time and care when using Abernethy Road during the works.

 

The Shire of Serpentine Jarrahdale appreciates your patience during this time.


 

Project summary

  • The Shire of Serpentine Jarrahdale is the fastest growing locality in Western Australia and rapid growth in population brings an increase in road traffic.
  • The local area of Byford fronting Abernethy Road is fast growing and with that, the capacity of Abernethy Road is rapidly approaching the limit for safe operation and will exceed that in the very near future.
  • Some members of our community have expressed concern with the current capacity and traffic safety of Abernethy Road and expressed a desire for it to be upgraded.

Anticipated future traffic volumes

  • By 2030: 10,800 to 16,800 vehicles per day will use Abernethy Road (in 2012 it was just under 2,849).

The current road won't cope

  • There is enough room in the current roadway (generally 28 metres wide) to fit 4 lanes (2 in each direction) plus turning lanes and a central median as well as footpath either side and street trees from around the Byford Secondary College extending towards the east.
  • Widening will be needed

Benefits the upgrade will bring

  • Reduce congestion.
  • Safer opportunities for turning (both at roundabouts and into/out of your driveways)
  • Safer opportunities for cycling and walking with shared footpaths and street lighting
  • Minimise accidents: Reported crash data shows there has been 69 crashes on Abernethy Rd between Kardan Boulevard and the South Western Highway (Jan 2012 – Dec 2016)
    • The majority were vehicles entering/leaving driveways or turning right at an intersection
    • The second higher were vehicles from 'one direction' e.g. rear end/side swipe type crashes
    • 82% property damages only
    • 12% required medical attention, and
    • 6% resulted in people being hospitalised, 0 fatalities

State Government expectations for Abernethy Road

  • Set out in Perth and Peel @ 3.5 million strategic documents Abernethy Road will transition from being a ‘local road’ into what is known as a ‘regional road’.

Current status

  • We are working with state agencies to relocate essential services like telecommunications, water, power etc.

Construction stages

Stage 1 - current

  • Site setup and clearing of vegetation

Stage 2 - current

  • The Shire is working closely with the following agencies to relocate essential services:
    • Telstra
    • NBN Co
    • ATCO Gas
    • Western Power
    • Water Corporation
    • Public Transport Authority

Stage 3

  • Upgrade of Beenyup Brook culvert crossing

The unexpected delays that have been experienced during the relocation of services have allowed the Shire to undertake a review of the existing plans for the creek crossing works. A new approach has been developed that will avoid the need for the prolonged road closure that has previously been communicated. It is now expected that any closures will be limited to short term closures and wherever possible will be undertaken outside of business hours to avoid inconveniencing surrounding schools and businesses. Information regarding any closures will be made available via our Facebook page and Roadworks website.

Stage 4

  • Road upgrade works within the rail reserve

These works require changes to rail signalling systems which are under the control of the Public Transport Authority. During this stage a complete closure of the crossing for a period of approximately 3 days will be required. The Shire is working closely with the Public Transport Authority to ensure that this happens at a time that will minimise disruption to surrounding schools and businesses. Information regarding any closures will be made available via our Facebook page and Roadworks website.

Stage 5 - current

  • Earthworks, drainage and pavement works
  • Stage 5 will commence as soon as possible after the completion of Stage 2

 

Media


Contact us

  • Our Infrastructure Team is happy to assist with any enquires regarding this project, please contact us.
  • Construction plans are available for the public to view at the Administration Office, 6 Paterson St, Mundijong and at the Mundijong Public Library.